Erosion control keeps loose soil on a cleared or graded site instead of in storm drains, streams and neighboring lots. Thrare Contracting supplies and installs silt fence, curb inlet protection and drain mats on metro Atlanta sites. Thrare quotes each job from the site address, the scope of the work and the erosion plan for the site.
What erosion control does Thrare supply and install?
Thrare Contracting supplies and installs three items: silt fence, curb inlet protection and drain mats. Contractors, builders and property owners in Atlanta, Fulton, Cobb and DeKalb counties request these items most often on clearing, grading and site-work projects. The table below shows where each item goes and what each item does.
| Item | Where it goes | What it does |
|---|---|---|
| Silt fence | Downhill edge and side slopes of disturbed ground | Slows runoff so soil settles out before water leaves the site |
| Curb inlet protection | Storm drain inlets in the curb line | Filters sediment out of runoff before runoff enters the storm system |
| Drain mats | Catch basins, area drains and low points | Keeps sediment and debris out of the drain while water passes through |
What is silt fence?
Silt fence is a fabric barrier staked along the downhill edge of disturbed ground. Silt fence slows runoff so soil settles out before the water leaves the site. Crews trench the bottom edge of the fabric into the ground and keep the fence upright. Sediment built up behind the fence has to be removed before the sediment overtops the fabric.
According to Georgia EPD general NPDES permit GAR100001, sediment traps, silt fences, wood mulch berms or equivalent sediment controls are required on all side slope and down slope boundaries of the construction area where a sediment basin is not attainable. The same permit requires mulch filter berms in addition to a silt fence on the site perimeter wherever construction stormwater, including sheet flow, may be discharged.
What is curb inlet protection?
Curb inlet protection is a filtering device placed at a storm drain inlet in the curb line. Curb inlet protection catches sediment before runoff enters the storm system. Builder lots, road work and utility trenches all expose curb inlets to muddy runoff.
Georgia EPD lists storm drain inlet protection in permit GAR100001 as one of the structural practices a construction site plan uses to limit the discharge of pollutants from exposed areas. A curb inlet that fills with silt stops working, so the device needs to be cleaned out on a schedule and after heavy rain.
What is a drain mat?
A drain mat covers or surrounds a drain and keeps sediment and debris out of the drain while water still passes through. Drain mats are used at catch basins, area drains and low points on a work site. Drain mats are also used at a drain that is exposed late in grading, after the perimeter controls are already in place.
Does a site need erosion control during clearing and grading?
Yes, on most sites that disturb soil. The Georgia Erosion and Sedimentation Act of 1975, O.C.G.A. 12-7-1 and following, requires erosion and sediment control on land-disturbing activity. The Georgia Soil and Water Conservation Commission publishes the Manual for Erosion and Sediment Control in Georgia, and most local plans follow that manual. Atlanta, Fulton, Cobb and DeKalb add their own permit rules, so the approved plan for the site sets what must go in.
According to Georgia EPD permit GAR100001, a construction site needs NPDES permit coverage when the land disturbance equals or exceeds 1 acre. Sites below 1 acre can still need local erosion control under the local ordinance for the jurisdiction.
How often are erosion controls inspected?
Georgia EPD permit GAR100001 requires certified personnel to inspect the site at least twice every 7 calendar days and within 24 hours of the end of a storm of 0.5 inches of rainfall or greater. Silt fence, curb inlet protection and drain mats that fail an inspection have to be repaired or replaced.
The same Georgia EPD permit requires a BMP failure that needs no new or replacement device to be repaired within 2 business days of discovery. A failure that needs a new or replacement BMP has to be operational within 7 days of discovery.
When does stabilization have to start?
Under Georgia EPD permit GAR100001, stabilization measures must start as soon as practicable on any part of the site where work has paused or ended, and in no case more than 14 days after the work stopped in that area. Seed, sod, mulch or paving all count as stabilization. Silt fence and inlet protection stay in place until the ground is stabilized.
How big is the sediment basin requirement?
Georgia EPD permit GAR100001 calls for a sediment basin with at least 1,800 cubic feet (67 cubic yards) of storage per acre drained, or equivalent control measures, until final stabilization. The permit requires the operator to remove sediment once the basin fills to 22 cubic yards per acre of drainage area. Silt fence and mulch berms serve as the equivalent controls where a basin does not fit on the site.
In what order does erosion control go in?
Erosion control goes in before the soil is disturbed and stays until the ground is stabilized. The order on most projects runs in five steps:
- Install perimeter silt fence before clearing starts.
- Clear and rough grade the site.
- Place curb inlet protection and drain mats as each drain is exposed.
- Inspect after each storm of 0.5 inches or more and repair any failure.
- Stabilize with seed, sod, mulch or paving, then remove the temporary controls.
Where do rock and recycled concrete come in?
Larger stone is used for construction entrance pads, check dams and rip rap at outlets. Recycled concrete in larger pieces can serve on some sites. See recycled aggregates and gravel base products, GAB, millings and rip rap.
How do I get erosion control quoted?
Send Thrare Contracting the site address, the scope of the clearing or grading and what your plan calls for. Thrare will confirm what Thrare can supply or install and quote the job. Request a quote or see grounds maintenance and commercial services.
Sources: Georgia Environmental Protection Division, NPDES General Permit GAR100001 (2023, in effect August 23, 2024); Georgia Erosion and Sedimentation Act of 1975, O.C.G.A. 12-7-1 and following; Georgia Soil and Water Conservation Commission, Manual for Erosion and Sediment Control in Georgia. Permit text read 2026-11-26.